  • Thursday, 25/02/2016

    There are many signs that the works on the thermal efficiency improvement of the building at pl. Łódzki 3 are going to finish earlier than expected.

  • Wednesday, 14/10/2015

    Although the range of works connected with the thermal efficiency improvement is wide, some progress can already be seen. Nearly all the windows (95%) in the building are replaced. The  insulation and elevation are being done. You can already admire first results – the elevation of the West wall of the building is finished. The thermal centre is also being modernised.

  • Friday, 25/09/2015

    On 08.07.2015 in the Vicechancellor's Office of the University of Warmia and Mazury there was a press conference about the thermal efficiency improvement of a building at pl. Łódzki 3. A day earlier the Vicechancellor signed an agreement with a contractor.

  • Thursday, 18/06/2015

    On June 2, 2015, the Minister of Environment represented by proxy Agnieszka Rendemann and Agnieszka Ignatowska, signed a contract with Professor Ryszard Górecki, the Rector of the University of Warmia and Mazury in Olsztyn, for financing the project "Comprehensive thermal efficiency improvement of teaching and administrative building of the University of Warmia and Mazury at pl. Łódzki 3 in Olsztyn".

    The total estimated cost of the improvement project amounts to PLN 2,780,893. The grant amounts to 80% of the total cost, i.e. PLN 2,224,714.

  • Monday, 27/04/2015

    The building has already been protected against bird breeding according to the guidelines of the Regional Directorate for Environmental Protection. Also the design phase has been completed by obtaining the valid building permits and the consent of the Conservator of Monuments of Warmia and Mazury for the works.